Schedule

The schedule below shows our current progress on the two phases.

On Phase 1, DOT&PF has completed design, completed an environmental document, and advanced half of the project to construction. Construction began in late spring 2018 and is scheduled to be complete by mid-summer 2021.

Phase 2 will begin at Sports Lake Road and tie into Phase 1 at Eagle Rock Drive. This phase will require some minor Right Of Way purchases, with acquisition 95% complete. Construction for Phase 2 is scheduled to begin in 2020 and continue until fall of 2023.

Project Schedule